Valle Vista Library Extension |
Valle Vista Library Extension
|
Location: |
43967 East Florida Avenue |
Project: |
Expansion from 2,400± square-feet to 5,000± square feet |
Project cost: |
$450,000 overall; $370,000 construction |
Project funding: |
$360,000 Redevelopment Agency funds |
|
$75,000 library funds |
|
$15,000 CDBG funds |
Status: |
Completed |
Benefits: |
Improved access to various library resources including literacy classes, computer instruction; elimination of structural deficiencies at existing facility; expanded hours of operation. |
|
|
|
|
|
|
|
|
|